What is the first step in the sequence of actions to temporarily remove a lockout/tagout after servicing?

Prepare for the OSHA 30hr test with comprehensive resources. Study with multiple-choice questions, get hints and explanations for each question. Ensure your success on the OSHA 30hr test!

Multiple Choice

What is the first step in the sequence of actions to temporarily remove a lockout/tagout after servicing?

Explanation:
The first step is to clear the machine of tools and materials. After servicing, you need the work area free of loose tools and nonessential items so nothing can strike or interfere with re-energizing, and so controls and safety devices remain accessible. This preparation ensures you aren’t introducing hazards when you start the equipment again. Only after the area is cleared would you verify that all workers are clear and proceed with removing the lockout/tagout and energizing to test or reposition the equipment. Clearing tools and materials sets the safe, unobstructed condition required before restoring power.

The first step is to clear the machine of tools and materials. After servicing, you need the work area free of loose tools and nonessential items so nothing can strike or interfere with re-energizing, and so controls and safety devices remain accessible. This preparation ensures you aren’t introducing hazards when you start the equipment again. Only after the area is cleared would you verify that all workers are clear and proceed with removing the lockout/tagout and energizing to test or reposition the equipment. Clearing tools and materials sets the safe, unobstructed condition required before restoring power.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy